The data in words
The critical path runs through the Foundry. The seed must launch by October 2028 so the Lattice reaches full power by June 2033. Ice launched after October 2035 cannot arrive before the deadline, so any slip in the doubling time comes straight out of the water. Earth-like Venus comes on 30 September 2036 in the simulation, 92 d before the deadline of 31 December 2036.
| Lane | Workstream or milestone | Start | End | Critical path |
|---|---|---|---|---|
| Science and proof | Proof experiments | 1 January 2027 | 31 December 2028 | |
| Science and proof | Cloud-life survey | 1 June 2027 | 1 December 2028 | |
| Science and proof | Gate: no native life | 15 December 2028 | ||
| Mercury | Seed foundry launches | 1 October 2028 | Yes | |
| Mercury | Ouroboros growth | 14 January 2029 | 22 June 2033 | Yes |
| Mercury | Helios Lattice built | 1 June 2030 | 22 June 2033 | Yes |
| Near Venus | Hesperus Veil built | 1 June 2030 | 30 June 2032 | |
| Near Venus | Braking Ring built | 1 June 2032 | 31 December 2033 | |
| Near Venus | Aegis Shield online | 15 June 2034 | ||
| Ceres | Ceres ice launches | 22 June 2033 | 21 October 2035 | Yes |
| Ceres | The Ring powers the Railheads | 17 August 2034 | ||
| Venus | Active cooling | 1 January 2033 | 30 June 2036 | |
| Venus | The Clear Rain | 19 January 2034 | ||
| Venus | CO₂ rain-out and sealing | 19 January 2034 | 30 June 2036 | |
| Near Venus | Ice caught and parked | 17 August 2034 | 15 December 2036 | Yes |
| Venus | Ice lowered, oceans fill | 30 June 2035 | 15 December 2036 | |
| Venus | Oxygen forging, acid sweep | 1 January 2035 | 30 September 2036 | |
| Venus | Genesis seeding | 30 September 2036 | 15 December 2036 | |
| Venus | Earth-like Venus (simulated) | 30 September 2036 | ||
| Venus | Deadline | 31 December 2036 |
| Workstream or milestone | Start | End |
|---|---|---|
| Proof experiments | ||
| Cloud-life survey | ||
| Gate: no native life (gate) | ||
| Seed foundry launches | ||
| Ouroboros growth | ||
| Helios Lattice built | ||
| Hesperus Veil built | ||
| Braking Ring built | ||
| Aegis Shield online | ||
| Ceres ice launches | ||
| The Ring powers the Railheads | ||
| Active cooling | ||
| The Clear Rain | ||
| CO₂ rain-out and sealing | ||
| Ice caught and parked | ||
| Ice lowered, oceans fill | ||
| Oxygen forging, acid sweep | ||
| Genesis seeding | ||
| Earth-like Venus (simulated) | ||
| Deadline |
The critical path
The critical path runs through the Foundry. The seed must launch by so the Lattice reaches full power by . Ice launched after cannot arrive before the deadline, so any slip in the doubling time comes straight out of the water.
Link by link: the seed spends in transit and lands on . It needs doublings of to reach full scale. The day it does, the Lattice reaches full power and the first Bricks leave Ceres, because only then is there power to throw them. At the other end, a Brick takes to fall to Venus, and the last one must arrive by , before the deadline. That fixes the last launch. The ice campaign is whatever time is left between the two, and the Railheads must throw in it.
Two other links are close behind. The Veil must close before active cooling starts on : the Foundry could build it in one doubling from , and it closes in . The Ring must be finished before the first Brick arrives on ; it is complete by .
Phase by phase
Proof: 2027 and 2028
The nine experiments run in parallel from and must pass by (Research Agenda). The cloud-life survey flies from and reports in . The gate falls on , after the seed has launched but before it lands: a credible sign of native life stops the program before the Foundry touches Mercury.
Growth: 2029 to 2033
The Foundry grows from to . Its output goes first into itself, then into the first Lattice Petals from , the Veil's slats from and the Ring from . The atmosphere simulation has not started yet; what governs this phase is the Foundry's growth curve and the dates on which it can afford each product.
Cooling: 2033 to 2036
Active cooling runs from to , and here the day-by-day simulation takes over. Until the Ring takes over the Railheads, they draw of the Lattice's , and cooling is starved of power. Even so, the Clear Rain begins on . From power is plentiful and the Exhaust runs at its limit, . The seas start to freeze on , all the CO₂ is down by , the Frost Towers reach their target on , and the last caps are sealed by .
Water: 2033 to 2036
Bricks leave Ceres from to . The Ring catches the first on and the last on . Lowering to the surface is planned from to . In the simulation, ice that lands while the air is below freezing stays frozen until the caps are sealed and the air is warmed. How that ice gets down at all is still open.
Breathing: 2035 and 2036
The Forges run from to , and the Aegis Shield has been on since . Once the caps are sealed the Veil opens and the simulated air warms to by . It is Earth-like on , the day the oxygen is complete, and Genesis seeding runs from then to . That leaves before the deadline.
What slips if the Foundry is slow
Full scale arrives at the landing date plus doubling times. So every day added to the doubling time pushes the Foundry's full scale, the Lattice's full power and the first ice launch back by days. A late seed launch does the same, day for day. What does not move is the deadline, and with it the last useful ice launch. The slip lands in three places.
- The water. The ice campaign shrinks from the front, so the Railheads must throw faster to deliver the same , or the ocean comes out shallower.
- The energy. The Lattice has fewer full-power years before the deadline. With only spare on its own, a doubling time only a little longer than uses that up: the Lattice alone no longer covers the demand, and the plan then depends on the Ring's recovered energy, which still leaves a margin.
- The schedule. The simulated Earth-like date at first holds, because it is set by when the Forges finish. A much slower Foundry cannot afford the Veil by its close date, and the simulated air misses the deadline.
To see the size of each effect, move the doubling time in the Explorer, or run:
pnpm calc --set foundry-doubling-days=62
If the Foundry cannot approach its doubling time at all, the decade is out of reach and the plan falls back to the multi-century route (Research Agenda).